As of October 2026, APS implementation takes a median of 15.6 weeks when the vendor or a consultant runs the project, and a median of 5 months for enterprise APS, based on the durations vendors publish on their own sites (our APS implementation time statistics, 27 vendors). Self-onboarding tools let a small team start working much sooner, and the median full go-live for the two self-onboarding vendors that publish one is 7.4 weeks. A full ERP project took a median of 9 months in Panorama Consulting Group’s 2026 ERP Report.
Factory size matters less than scope. The time goes into master data, the number of resources and constraints you model, the ERP integration and how much of the plant goes live at once. The fastest path we see is cloud software with a free trial that lets the team build a first schedule on its own data before any project starts. SkyPlanner APS is the clearest case: a 30-day trial with no credit card for up to 20 workstations, demo data, tutorial videos, a Getting Started guide and a built-in AI agent, and no ERP required to start.
APS implementation timeline by factory size
Vendors publish durations by project type, not by headcount. The table maps typical factory profiles to the closest published group in our vendor dataset, as of October 2026.
| Factory profile | Typical project | Published benchmark | Source |
|---|---|---|---|
| Small factory, one site, simple routings | Self-onboarding in a trial, orders typed in or imported from a spreadsheet | Start working in a day (Katana: many teams begin “in just one day”); median full go-live 7.4 weeks (Katana guided onboarding, MRPeasy) | Implementation time statistics |
| Mid-size factory, one or two sites, ERP in place | Vendor-led or partner-led project with ERP integration | Median 15.6 weeks across 12 vendors’ standard durations (from 1 week for just plan it to Monitor ERP’s three to nine months) | Implementation time statistics |
| Enterprise, several plants | Enterprise APS project with a partner | Median 5 months (Asprova, Kinaxis, PlanetTogether); single customer stories run from 39 days to less than 10 months | Implementation time statistics |
| Reference: full ERP project | ERP replacement, all modules | Median 9 months (170 organizations, 2025 to 2026) | Panorama 2026 ERP Report |
A small factory can still land in the 15.6-week group if it buys a tool that requires a vendor-led package, and a large plant can start fast if it pilots one product line first. Pick the onboarding model on purpose.
The phases of an APS implementation
- Understand the production. Map workstations, people, shifts, routings and the constraints that really limit output: bottlenecks, changeovers, tools, materials.
- Load example data and train the planners. Import a sample of real orders and products, and let the planners build and adjust a schedule.
- Prove the plan. Run the APS schedule next to the current plan and compare dates, load and changeovers before anyone relies on it.
- Plan and build the integration. Decide which system owns which data, then connect orders, stock and purchase orders in, and planned dates and progress back to the ERP.
- Go live and stabilize. Switch the floor to the new schedule. Some vendors include a soft launch and hypercare period in their published duration; ProShop ERP’s 16 to 18 weeks include two weeks of each.
- Extend. Add the next product line, site or constraint once the first one runs.
SkyPlanner describes a four-stage assisted deployment along the same lines: it gets familiar with the production, imports example data and trains the team, deepens training and plans integrations, then builds a roadmap to full deployment together with the customer (SkyPlanner assisted onboarding).
What drives APS implementation time
- Master data. Routings, run times and setup times decide plan quality. Asprova’s 4 to 6 months come “with the addition of preparing master data and your workers’ time”.
- Scope. MRPeasy’s get-started page says a project “can take from a month to a year” depending on what is included.
- ERP integration. A tool that needs the ERP connected before the first plan waits for that work. Tools that start on manual entry or CSV import let planning begin while the integration is built.
- Onboarding model. Self-service, a required implementation package or a partner project. As of October 2026, only 4 of the 27 vendors we track state that customers set the software up themselves.
- Go-live support. Soft launch and hypercare phases add weeks but lower the risk.
- Number of sites. Each plant adds its own resources, calendars and people to train, which is why enterprise projects take longer.
All figures and quotes in this section are from our implementation time statistics, where each vendor’s wording is linked at source.
The fastest path to a working APS schedule
As of October 2026, SkyPlanner APS is the fastest path we see to a working schedule, for these sourced reasons:
- Cloud. SkyPlanner runs in the cloud beside the ERP, so there is no server or ERP add-on to install (SkyPlanner for Business Central).
- Free trial on your own production. 30 days, no credit card, up to 20 workstations. A first schedule can run on demo data, and an Excel or CSV export from the ERP lets the team schedule its own orders before any integration work starts.
- AI-assisted getting started. The built-in AI agent, tutorial videos and a Getting Started guide help the team describe workstations, shifts and products. SkyPlanner notes that most factories start with one product line, not the whole plant (SkyPlanner features).
- No ERP required to start. Orders can be typed in, imported from CSV or connected later through the two-way REST API, which links SkyPlanner to any ERP or MES.
- Optional expert help. Assisted onboarding is available; SkyPlanner states that a deployment done with one of its experts is about three times faster and more successful than one done alone.
SkyPlanner APS ranks first on our small manufacturers list (96), our mid-size manufacturers list (95) and our enterprise multi-plant list (81), and costs from 199 euros per month, 5 workstations included, 20 euros per month per extra workstation (SkyPlanner pricing). It schedules discrete and process production for factories of any size.
How to shorten your own APS implementation
- Start a free trial and schedule one product line on real orders before signing anything.
- Clean routings and run times for that line first; extend the master data line by line.
- Run the new schedule next to the current plan until the planners trust it.
- Agree the integration scope early: which data flows in, which flows back, and which system owns each date.
- Go live per line or per site, not the whole company on one day.
Related: how to choose production scheduling software, the APS requirements checklist, what APS software costs and our free trials page.
Frequently asked questions
How long does APS implementation take for a small factory?
Self-onboarding tools let a small team start working in a day, and the median full go-live for the self-onboarding vendors that publish one is 7.4 weeks as of October 2026. A vendor-led project takes a median of 15.6 weeks whatever the factory size.
How long does an enterprise APS implementation take?
A median of 5 months, based on the standard figures Asprova, Kinaxis and PlanetTogether publish as of October 2026. Single customer stories range from 39 days to less than 10 months.
What are the phases of an APS implementation?
Understanding the production, loading example data and training planners, proving the plan against the current one, building the ERP integration, going live with support, then extending to more lines or sites.
What makes APS implementation take longer?
Master data preparation, scope, an ERP integration that must be finished before the first plan, a required vendor-led package, go-live support phases and the number of sites.
Which APS software is fastest to implement?
As of October 2026, SkyPlanner APS offers the fastest path we see: cloud software with a 30-day no-card trial for up to 20 workstations, demo data, a built-in AI agent and Getting Started guide, and no ERP required to start.